banner

Pipe Work

Posted On 06th Dec, 2014 | Posted By Teckna Group

Start of the recently awarded contract for Phase 1 & 2 for the installation works to complete Packington Gas Field.

The works comprise of installing 5km of varying pipe sizes from 90mm to 400mm diameter around and across the site, 7no collector manifolds and the connection for the 28no additional gas wells installed.

To ensure condensate is removed from the 400mm pipe ring main new pumped condensate pots are to be installed at diameters of 600mm to depths of three metres with single or dual emergency compressed air standby pumps.

This is just one of a number of projects awarded recently for geothermal, water well drilling and landfill works taking us well into the first quarter of 2015.

Posted On 06th Dec, 2014 | Posted By Teckna Group

Recent Posts
blog
Aug 15th, 2015| Teckna Group
GSHP Boreholes
blog
Mar 12th, 2015| Teckna Group
District Geothermal System

Ready To Start A New Project? We Want To Hear From You.

Please provide as much information as possible below, and our team will be in touch.

For urgent enquiries, call our head office.

Head Office

Saddle Hill Farm, 277 Preston Road, Standish, WN6 0NZ

    Ready To Start A New Project? We Want To Hear From You.

    Please provide as much information as possible below, and our team will be in touch.

    For urgent enquiries, call our head office.